Suntop Solar Farm News

Project Update | Quarter Ending Dec 2021

Project Update | Quarter Ending Dec 2021

The project has completed construction activities and has demobilized the temporary construction facilities from the site.  Commissioning activities are complete and the project is generating power into the grid while it advances through the Hold Point Testing process...

read more
Project Update | Quarter Ending July 2021

Project Update | Quarter Ending July 2021

Construction Progress: The project is nearing completion of the mechanical and electrical construction phase with all mechanical and HV electrical installation complete.  Module installation is at 60% and the completion of these works along with the DC harnessing and...

read more
Project Update | Quarter Ending December 2020

Project Update | Quarter Ending December 2020

Following on from last quarter when works began, the Early Works campaign has now reached completion. This included upgrades to Renshaw-McGirr way, two site access points off Suntop Road, and the substation access road which is internal to the Project site. The...

read more
Substation Modification Approval

Substation Modification Approval

In October 2019, the Department of Planning, Industry and Environment approved a Modification to the Development Approval to relocate and amend the layout of the substation. The purpose of this is to allow for improved safety during construction of the substation by...

read more